Foundry Business and Market Trend Report | August 2023
September 30, 2023
Key Takeaways:
TSMC 2nm Construction Updates:
- TSMC's 2nm construction sites are likely to be located at Fab12B and Fab20 in Hsinchu, and Fab22 in Kaohsiung.
- As for Taichung, there might be pending in the schedule due to environmental concerns.
TSMC Arizona Fab 21 Operation Updates:
- TSMC’s Fab 21 operations has been significantly delayed by initial tool installations due to constructions and administrative delays, followed by prolonged EUV lithography tool setups.
- The short-loop risk production, the prelude for site qualification, is estimated to be a quarter delay from 3Q23 to 4Q23.
- The pilot-line after the successful site qualification is expected to be 2 quarters delay due to longer-than-expected EUV lithography tool setup.
CanSemi Capacity Expansion Plan Updates:
- CanSemi’s P3 construction commenced 3Q22 and is projected to reach MP in 2H24.
- The primary products are expected to include IGBT, MS, and BCD, with production capacities of approximately 33~35%, 27~29%, and 36~38%, respectively.
Table: CanSemi Capacity Expansion Plan in Y2023~Y2025
The information we shared is only a short excerpt of our monthly report. If you have further interest in our research and findings, we would be happy to provide you with a more detailed and comprehensive report that includes additional insights and data points. Please contact us to access our full insights.